KJAB 100,000 Watts of Gospel Power!

To God be the glory for the great things He has done!  We are looking forward to hearing from those of you who can now hear us.  Drop us and email on the contact page and let us know where you heard KJAB.  Help us get the word out that we are back on the air at full power. 

Expected Expenses for the KJAB Expansion 

ITEM COST PAID
Transmission Line 10,525.50 PAID
Nautel 1Kw Exciter 7,467.00  
Tube for Transmitter 1865.00 PAID
Kit to Re-tune Transmitter 2,288.11  
Engineer Expense (Tower Setup) 1,041.12 PAID
Engineer Expense (Antenna Install) 1,522.38 PAID
Tower Climber 6,500.00 PAID
Patch Panel, Rigid line, Flanges, etc 6,150.00  
Surge Protection 4,000.00  
Bird Meters 1,392.00  
Composite DA 359.00  
5 Ton Air Conditioner 3,116.09 PAID
Air Conditioner Duck Work 3,000.00 PAID
Air Conditioning Install 500.00  
Electrical Supplies 2,622.22 PAID
Culvert 225.00  
Bobcat Rental 200.00 PAID
Rock Delivery 75.00 PAID
Miscellaneous 1,627.17  
Electrical Supplies 243.84 PAID
Meals/Food 158.45 PAID
Engineer Hotel Expense 113.76 PAID
Additional Engineering Expense 3,331.90 PAID
Additional Electrical Supplies 428.12 PAID
Shipping Charges 63.97 PAID
Construction Materials 411.37 PAID
Parts for Studio Transfer Authorization 680.94  
FCC Attorney Retainer 1,000.00 PAID
Andrew Line Dehydrator 1,026.62  
Engineering for Studio Trans Auth 1,000.00 PAID
Total Minus What is Paid 25,715.84  
Money available as of 6/17/13 408.44  
Adjusted Total Need 24,879.28  

  

Watch Our Expansion Video
and Click Below to
Read More about the Expansion

 

 Look What God Has Done